Chemin d’Ablis (FR)

support our internal process

Specsheet

Model :MM92 to MM82

Intervention :Fire damage

Objectives : Turbine dismantling and rehabilitation

Challenges

  • Avoid blasting – Do not compromise the integrity of the nacelle to allow inspection.

  • Dismantling – he nacelle’s center of gravity was shifted following the fire.

Project Management

  • Advice on civil engineering rehabilitation
  • Dismantling of the damaged machine
  • Organization of transport and lifting operations
  • Partial refurbishment to improve performance
  • Assembly and start-up
  • Component recycling
  • Re-installed secondhand turbine